MATERIALS REQUIREMENTS PLANNING WORKSHEET  
Level On Hand Order size Lead time
A B C D
0 A 0 0 < Number of these in each A
0 B 0 0 < Number of these in each B
1
1
`
Order Quant:
Lead Time:
Level 0
Week
Gross requirements
Fill in any previously ordered materials. Show for the arrival period.
Scheduled receipts
On hand
  Planned releases      
Order Quant:
Lead Time:
Level 0
Week
Gross requirements
Scheduled receipts
On hand
  Planned releases        
 z 
 Order Quant: 
 Lead Time: 
 Level  1
Week
Gross requirements
Scheduled receipts
On hand
  Planned releases        
 Order Quant:   Lead Time: 
 Level  1
Week
Gross requirements
Scheduled receipts
On hand
  Planned releases