A small office building construction project requires completion of the tasks shown in this precedence diagram. 
The corresponding CPM data file is as follows.
0 1 4 Form 1 2 2 Pour 2 3 14 Cure 3 4 2 Strip 3 6 8 Frame 4 5 5 Curtain walls 4 8 10 Plumbing 4 7 10 Risers 4 10 1 Doors 4 13 16 Electrical walls 4 12 3 Balance elevator fittings and frames 5 6 5 Sash glaze 6 7 5 Spray fireproof 6 13 5 Insulate wall, etc. 7 8 5 Ceiling ducts & fixtures 8 9 3 Test 9 13 3 Insulate mechanical 10 11 2 Part masonry 11 13 0 Dummy 11 12 0 Dummy 12 14 3 Finish masonry 13 14 3 Lathe 14 15 5 Plaster 14 17 3 Marble work 15 16 0 Dummy 15 17 0 Dummy 15 18 3 Tiling 18 19 0 Dummy 18 20 5 Paint (part) 19 20 5 Finish mechanical 20 21 1 Finish paint 21 22 4 Caulking & clean up
|